Guide · BESS in Mexico
BESS in Mexico: what they are for, what the regulation says and how the contracts work
In Mexico, an industrial BESS is installed mostly to cut what the plant pays CFE: it discharges in peak hours, cuts demand and corrects the power factor. Since April 2026 the regulation has been clear: if the system only serves your plant, it does not require a storage permit.
Reviewed by Mario René Córdova de la Peña, electrical engineer and CTO of ENEGRIN, in November 2026
BESS in Mexico in one minute
- A BESS is an energy storage system. It charges in base hours and discharges in peak hours.
- It lowers the peak energy, capacity and distribution charges, and corrects the power factor.
- Measured savings with ENEGRIN BESS are 27% to 37% of the bill, if you buy the system.
- The 2026 regulation recognizes five modes. The one for an industrial plant does not require a storage permit.
- You can get one with no investment, paid out of the savings, or buy it.
In this guide
To apply this to your plant, an ENEGRIN engineer replies the same business day.
Talk to an engineer1. Why industry installs BESS in Mexico
Because of how the industrial tariff bills. In Mexico, energy costs a different amount depending on the hour, and demand is billed separately.
- Peak hours are expensive. In November 2026, a peak kWh costs between 1.7 and 2.1 times a base one, depending on the division, including transmission, CENACE and ancillary services.
- You pay for the peak all month. Each kW of demand in peak hours costs MXN 246.78 to MXN 386.38 a month, depending on the division.
- The power factor requirement rose. Since April 2026, the Grid Code has required a power factor of at least 0.97 at plants of 1 MW or more.
- The grid fails. An outage or a voltage disturbance stops whole lines, and a BESS can keep the plant running.
A BESS addresses all four with one piece of equipment: it charges in base hours, discharges in peak hours, cuts the peak, corrects the power factor and provides backup.
What a BESS is and how it works · This month’s GDMTH tariff by division
2. What the regulation says
Storage has had its own rules since 2025. The Electricity Sector Law defines it, and in April 2026 the National Energy Commission (CNE) published the provisions in force, which replaced those of March 2025.
| Mode | What it is |
|---|---|
| At an industrial plant | The one for an industrial plant. It shares the connection point with the plant and serves only the plant. |
| Self-consumption | Integrated into the facilities of a self-consumption scheme. |
| Associated with a power plant | Next to a renewable power plant that sells to the market. |
| Of the transmission or distribution grid | Installed by the transmission operator or the distributor as part of its infrastructure. |
| Not associated | Stand-alone. It draws energy from the grid and injects it on its own account. |
Does your BESS need a permit?
Choose how the system will be used.
Use of the system
No storage permit required
It is your plant’s BESS. The provisions treat it as part of your facilities.
In return, it must not inject energy into the grid at your connection point, and the stored energy cannot be sold.
No storage permit required
A system integrated into the facilities of a self-consumption scheme does not require a storage permit, as long as its power is equal to or lower than the demand of the consumption center.
The power plant does require a generation permit if it is 0.7 MW or more.
A CNE permit is required
A stand-alone system, one that is not part of a power plant or of a site that uses its energy, requires a storage permit from 0.7 MW.
Every system that takes part in the Wholesale Electricity Market needs a permit or an authorization, and a market participant to represent it.
3. How much a BESS saves
It depends on your tariff, your division and how your plant uses energy. On ENEGRIN BESS operating in Mexico, measured savings on the CFE bill range from 27% to 37%. Those are the savings of a customer who buys the system. Under shared savings you invest nothing and save up to 5% of your bill.
| Bill charge | What happens with a BESS |
|---|---|
| Peak energy | The BESS discharges in that band and your plant draws from the BESS. It lowers what you pay for the most expensive energy of the day. |
| Capacity | By cutting peak-hour demand, the demand you are billed falls and this charge with it. Per kW cut, it is the charge that falls the most. |
| Distribution | Falls only if the BESS also cuts your highest peak of the month, which may fall outside peak hours. |
| Power factor | The BESS solution corrects it, with the capacitors that come with it. A surcharge shrinks or turns into a credit, and an existing credit grows. |
| Base energy | Rises: the BESS charges in that band what it delivers at peak, plus conversion losses. It is the cheapest energy of the day. |
Your plant’s number is calculated with your consumption data. Calculate what cutting your peak is worth
4. How the contracts work: no investment, or buying the system
Several companies in Mexico offer BESS without you buying the equipment. The difference is what you pay each month and what happens in a month with no savings.
| Model | What you pay each month | In a month with no savings |
|---|---|---|
| Fixed rent | A fixed rent for the equipment | You pay the rent |
| Service fee | A fixed or indexed fee for the service | You pay the fee, unless the contract says otherwise |
| Shared savings (ENEGRIN) | A percentage of the measured savings | You pay nothing |
| Purchase | The price of the system, and then its operation and maintenance | Each month’s savings are yours |
What a BESS costs and what each model includes · ENEGRIN’s two contracting models
5. BESS companies in Mexico: the three types
| Kind of company | What it does | What to ask |
|---|---|---|
| Manufacturer or distributor | Sells the equipment. | Who will operate it every day, and with which management system. |
| Integrator | Designs and installs with third-party equipment. | Whether the management system is built for Mexico’s tariffs or is the generic factory one. |
| Energy service company | Supplies the system, operates it and charges a rent, a fee or a share of the savings. | How it measures savings and what happens in a month with no savings. |
ENEGRIN is the third type: it designs, installs and operates BESS at industrial plants in Mexico, and is based in Chihuahua.
To compare proposals from any company, ask for four things in writing: the method for measuring savings, the guarantee against your bill, the draft contract and who operates the system. How to choose a BESS provider
6. What sets a good project apart
- The management system. A BESS saves because it decides every day when to charge and when to discharge. Ollin EMS, ENEGRIN’s system, calculates with the charges of your CFE tariff.
- Measurement. Two certified meters and your tariff’s formulas, so that any auditor can verify the savings.
- Reconciliation. At ENEGRIN, the forecast bill matches the actual bill by 99.98% on average.
- The guarantee. By contract, you never pay more than you would have paid without the system.
7. Frequently asked questions
What is a BESS used for in Mexican industry?
Mostly to cut what the plant pays CFE: it discharges in peak hours, cuts demand and corrects the power factor. It also provides backup during outages.
How much does a BESS save in Mexico?
On ENEGRIN BESS operating in Mexico, measured savings on the CFE bill range from 27% to 37% if you buy the system, depending on season and consumption pattern. Under shared savings, with no investment, you save up to 5%.
Is it legal to install a BESS at my plant?
Yes. The storage provisions of the National Energy Commission, in force since April 2026, regulate five modes. The one for an industrial plant is a BESS that shares the plant’s connection and serves only that plant.
Does a BESS need a CNE permit?
If it only serves your plant, no. But a request for studies must be filed with CENACE, because the BESS technically changes your plant’s grid connection, and it must meet the technical standards.
Do I have to buy the BESS?
No, you do not have to. Some companies supply the system and charge a rent, a fee or a share of the savings. ENEGRIN works with shared savings and also sells the system.
Which companies install BESS in Mexico?
There are manufacturers that sell the equipment, integrators that install it and energy service companies that also operate it. ENEGRIN is the last of these.
More on BESS
- What is a BESSIts parts and what it does at each hour of the day
- Peak shavingCutting the demand peak, with a calculator
- Grid CodeWhat it requires of your plant and how to comply
- Capacitor bankWhat it is for and how to size it
- Backup during outagesBESS, diesel generator or UPS
- What a BESS costsThe contracting models and what you pay in each
- How to choose a providerWhat to ask for in writing
- Permits for a BESSWhat the storage regulation requires
Send us your GDMTH bill and we’ll tell you which charge can be reduced.
An ENEGRIN engineer reviews it and replies the same business day. If you would rather estimate the savings of a BESS yourself, use the Ollin Simulator: it asks you to create an account with your company email.
Sources
- CNE, general administrative provisions for integrating electricity storage systems into the National Electric System, Official Gazette (DOF), April 16, 2026: storage modes, a plant’s BESS (sections 4.1 to 4.6) and permits.
- Electricity Sector Law (Ley del Sector Eléctrico), Official Gazette (DOF), March 18, 2025, current text from the Chamber of Deputies: article 3, section L, and articles 19 and 82 to 85.
- Regulations of the Electricity Sector Law, Official Gazette (DOF), October 3, 2025: article 193: when a storage permit is required.
- CFE, “Tarifas finales del Suministro Básico” (final basic supply tariffs), effective November 1, 2026, Official Gazette (DOF): GDMTH tariff charges by division.
- CRE, Grid Code (Código de Red), RES/550/2021, Official Gazette (DOF), December 31, 2021: section 2.4: power factor of 0.97.